KEY INFORMATION
|
| Procurement Method |
: |
ICT |
| Tendering Method |
: |
Open Tendering Method |
FUNDING INFORMATION
|
| Budget and Source of Funds |
: |
Development Budget Grant/Credit |
| Development Partner (if applicable) |
: |
IDA |
PARTICULAR INFORMATION
|
| Project/Programme Name (if applicable) |
: |
|
| Tender/Proposal Package No |
: |
URP/RAJUK/W-1 |
| Tender/Proposal Package Name |
: |
Construction of 10 Storied plus 2 Basements Office Building with Research, Training and Testing Laboratory Facilities for Urban Resilience Unit, RAJUK |
| Date of Advertisement |
: |
08/11/2019 |
| Date of Notification of Award |
: |
14/10/2020 |
| Date of Contract Signing |
: |
20/10/2020 |
| Proposed Date of Contract Completion |
: |
April 2022 |
| No. of Tenders/Proposals Sold |
: |
16 |
| No. of Tenders/Proposals Received |
: |
3 |
| No. of Tenders/Proposals Responsive |
: |
3 |
INFORMATION ON AWARD
|
| Brief Description of Contract |
: |
The Structural System of the building’s superstructure mainly comprises of Steel Frame with Steel Deck and Concrete Core. Main Components of the Works: Part A: General Site Facilities, Part B: Civil Works (including Steel Works), Part C: Sanitary, Plumbing & Water Supply Works, Part D: Electro-Mechanical Works (comprises with D-1: Internal Electrification Works, D-2: Passenger Lift, D-3: CCTV & PA System, D-4: Networking System, D-5: Access Control System, D-6: Telephone System, D-7: 1250 KVA Sub-Station, D-8: 630 KVA Diesel Generator, D-9: Fire Detection System, D-10: Fire Protection System, D-11: Fire Separation Doors, D-12: On-Line UPS, D-13: Supply, Installation, Testing & Commissioning of HVAC System, D-14: Car Parking System & D-15: Integrated Building Management System (IBMS)) and Part E: Environmental Monitoring. Duration of Works Completion: 18 Months from the date of Commencement of Works |
| Contract Value |
: |
BDT 1,149,999,833.87 (In Words: Bangladesh Taka One billion One hundred Forty Nine million Nine hundred Ninety Nine thousand Eight hundred Thirty Three and Paisa Eighty Seven only) |
| Name of Supplier/Contractor/Consultant |
: |
China State Construction Engineering Corporation Ltd. |
| Location of Supplier/Contractor/Consultant |
: |
Address-1: No. 15, San Li He Road, Haidian District, Beijing, China
Address-2: House-4, Road-6, Baridhara, Dhaka, Bangladesh |
| Location of Delivery/Works/Consultancy |
: |
Dhaka |
| Is the Contract Signed with the same person stated in the NOA |
: |
Yes |
| If No give reason why |
: |
|
| Was the Performance Security provided in due time? |
: |
Yes |
| If No give reason why |
: |
|
| Was the Contract Singed in due time? |
: |
Yes |
| If No give reason why |
: |
|
ENTITY DETAILS
|
| Name of Authorised Officer |
: |
Abdul Latif Helaly |
| Designation of Authorised Officer |
: |
Project Director & Chief Engineer (Implementation) |